Procedure:
The field procedure and booking of staff reading is done in the same way as explained in the height of instrument method (each reading is entered on a different line in the appropriate column, except at a change point, where a FS and BS occupy the same line). However the data booking is performed as shown in the Table below.
Tabulation:
Calculations:
1. The difference in elevation between any two successive points (say A and B) can be calculated as: Elevation difference between A and B = first reading at A – second reading at B
2. NOTE, for any two successive staff readings:
- Second reading smaller than first reading represents a Rise (The sign of elevation difference is positive).
- Second reading greater than first reading represents a Fall (The sign of elevation difference is negative).
3. If the elevation of the first point is known, then the elevation of the second point can be calculated as: Height of B = height of A + rise (in rise case) or Height of B = Height of A – fall (in fall case)
Check: